9.Congurationviadisplayandoperatingunit
9.5 Mountingcorrection(oset)
9.5.1 Performingawetadjustment
Zero point will be taken from measurement in operation.
Requirement
■
Deviation ≤ 20 % of the measuring range.
■
Absolute vacuum with absolute pressure measuring instruments.
Not to be carried out without suitable equipment.
1. Open the operating menu with [↵].
Select “Basic setting” and conrm with [↵].
2. Select “Application” and conrm with [↵].
3. Select “Pressure” and conrm with [↵].
4. Select “Mounting corr.” and conrm with [↵].
5. Select “apply” and conrm with [↵].
Current measured value will be used as the new zero
point.
9.5.2 Performing a dry adjustment
The mounting correction is registered manually via the dry adjustment. For all future
measurements, the mounting correction will be subtracted.
Requirement Deviation ≤ 20 % of the measuring range.
1. Open the operating menu with [↵].
Select “Basic setting” and conrm with [↵].
2. Select “Application” and conrm with [↵].
3. Select “Pressure” and conrm with [↵].